Construction and Installation Supervision

The aim of construction and installation supervision is to improve plant safety and availability in new plant and during overhauls.

The construction and installation supervision team represents the interests of the customer vis-à-vis the supplier. Compliance with contractual stipulations is monitored in accordance with instructions and standards.

This field of activity covers relevant power plant components such as:
  • Structural steelwork
  • Boiler components
  • Piping
  • Flue gas desulfurization
  • Turbine generators
  • Pumps
Assurance of quality in manufacture and installation is achieved by:
  • Review of licenses, certificates and documentary evidence
  • Monitoring of construction and installation in progress
  • Inspection of welding work performed
  • Checking of rubber lining and corrosion protection work to be performed
  • Witnessing or performance of non-destructive testing and verification of the results
  • Final inspection of the finished components and review of the documentation

Construction and installation supervision is based on the VGB Standards, which are derived from the exchange of experience in VGB committees and from the analysis of damage and failures.